This past Monday (January 24, 2022) we began the first phase of the public notification, which takes 60 days to complete.

Immediately afterwards there is another public notification stage which takes 45 days.

At the end of these 105 days, with Hashem’s help, the property we are currently using at 33 Lachish will belong to the Ahavas Shalom Amuta.

At the same time, we are working expeditiously with the architect on the plans so that we can submit our application for a building permit. We must then wait for the city to approve our plans, and then we can BUILD!